This is Sakakibara. I will give the conclusion first. Multiplying the repair cost estimate directly by the 7.1% year-on-year rise in corporate goods prices is not appropriate. The Corporate Goods Price Index is an average of the prices of "goods" traded between companies; it does not measure the price of repair work itself. It is more accurate to review the repair cost estimate work item by work item, separating materials from labor.
What the 7.1% measures
The October Domestic Corporate Goods Price Index (preliminary), released by the Bank of Japan on November 12, 2026, rose 7.1% from a year earlier and 0.7% from the previous month. It is an average of the prices of 515 items of goods traded between companies, weighted by transaction value, and services are not covered. It does not include contract prices for construction work or the wages of tradespeople.
What lies inside the same 7.1% differs greatly by field.
| Group | Year-on-year | Items involved in repairs (examples) |
|---|---|---|
| Nonferrous metals | Up 31.7% | Copper pipes, electric wires and cables |
| Chemicals and related products | Up 15.5% | Paints, synthetic resins |
| Plastic products | Up 14.1% | Resin pipes and fittings |
| Lumber and wood products | Up 9.0% | Plywood, sawn lumber |
| Metal products | Up 6.5% | Aluminum sashes, locks and building hardware |
| Iron and steel | Up 6.3% | Steel materials such as galvanized steel sheets |
| Ceramic, stone and clay products | Up 5.3% | Cement, ready-mixed concrete, tiles |
| General purpose machinery | Up 3.2% | Pumps, commercial air conditioners |
In the same month, import prices rose 24.8% from a year earlier on a yen basis and 19.2% on a contract currency basis. This shows that it is not only the weak yen; the prices of the goods themselves bought overseas are rising.
Repair costs are not decided by "materials" alone
The price of repair work is decided by the cost of materials plus the labor of tradespeople, scaffolding and transport, and the general contractor's overhead. What the Corporate Goods Price Index directly reflects is only the materials and equipment part of this. As a measure closer to the work itself, the Ministry of Land, Infrastructure, Transport and Tourism's "construction cost deflator" has a "building repair" series covering renovations and repairs that improve a building's function or useful life. Monthly values are released with a lag of about 2 months, and the statistical table dated November 13, 2026 (Reiwa 8) includes figures up to August 2026 (Reiwa 8).
How to review the estimate
- Divide the planned work into items such as piping, exterior walls and roof, equipment, and interior finishes.
- For each work item, check the rough proportions of materials and labor on the quote. Work with a lot of copper piping or electric wiring tends to show a large rise in material costs, as in the table above.
- When using a past quote, check its date, restate it using the growth in the construction cost deflator (building repair), and then compare it with a new quote.
From here on, this is my opinion
If you apply one rate to all the work, it can happen that the estimate falls short for work with a lot of piping or electrical equipment and is too high for work that is mostly interior finishes. I think it is better to restate the estimate according to what each piece of work consists of.