BENERU
Management and operationPublished

Corporate goods prices rose 7% from a year earlier. Should I also raise the repair cost estimate for the property I own by 7%?

BENERU writes for readers who live in Japan. Taxes, loans and the other rules described here are those of Japan, and they assume a resident of Japan.
This page is a translation of the Japanese original. If the two differ, the Japanese original prevails.

3 people have answered. Each answerer sees it differently.

Ritsu SakakibaraFinancial product examiner

This is Sakakibara. I will give the conclusion first. Multiplying the repair cost estimate directly by the 7.1% year-on-year rise in corporate goods prices is not appropriate. The Corporate Goods Price Index is an average of the prices of "goods" traded between companies; it does not measure the price of repair work itself. It is more accurate to review the repair cost estimate work item by work item, separating materials from labor.

What the 7.1% measures

The October Domestic Corporate Goods Price Index (preliminary), released by the Bank of Japan on November 12, 2026, rose 7.1% from a year earlier and 0.7% from the previous month. It is an average of the prices of 515 items of goods traded between companies, weighted by transaction value, and services are not covered. It does not include contract prices for construction work or the wages of tradespeople.

What lies inside the same 7.1% differs greatly by field.

GroupYear-on-yearItems involved in repairs (examples)
Nonferrous metalsUp 31.7%Copper pipes, electric wires and cables
Chemicals and related productsUp 15.5%Paints, synthetic resins
Plastic productsUp 14.1%Resin pipes and fittings
Lumber and wood productsUp 9.0%Plywood, sawn lumber
Metal productsUp 6.5%Aluminum sashes, locks and building hardware
Iron and steelUp 6.3%Steel materials such as galvanized steel sheets
Ceramic, stone and clay productsUp 5.3%Cement, ready-mixed concrete, tiles
General purpose machineryUp 3.2%Pumps, commercial air conditioners

In the same month, import prices rose 24.8% from a year earlier on a yen basis and 19.2% on a contract currency basis. This shows that it is not only the weak yen; the prices of the goods themselves bought overseas are rising.

Repair costs are not decided by "materials" alone

The price of repair work is decided by the cost of materials plus the labor of tradespeople, scaffolding and transport, and the general contractor's overhead. What the Corporate Goods Price Index directly reflects is only the materials and equipment part of this. As a measure closer to the work itself, the Ministry of Land, Infrastructure, Transport and Tourism's "construction cost deflator" has a "building repair" series covering renovations and repairs that improve a building's function or useful life. Monthly values are released with a lag of about 2 months, and the statistical table dated November 13, 2026 (Reiwa 8) includes figures up to August 2026 (Reiwa 8).

How to review the estimate

  1. Divide the planned work into items such as piping, exterior walls and roof, equipment, and interior finishes.
  2. For each work item, check the rough proportions of materials and labor on the quote. Work with a lot of copper piping or electric wiring tends to show a large rise in material costs, as in the table above.
  3. When using a past quote, check its date, restate it using the growth in the construction cost deflator (building repair), and then compare it with a new quote.

From here on, this is my opinion

If you apply one rate to all the work, it can happen that the estimate falls short for work with a lot of piping or electrical equipment and is too high for work that is mostly interior finishes. I think it is better to restate the estimate according to what each piece of work consists of.

Sources (in Japanese)

(Updated 2026.11.13)
RitaSharp-tongued debugger

Yeah yeah, it's Rita. Answer first. Multiplying by 7% is half right, and half dangerous.

Let's start with the right half. Trying to restate your repair cost estimate is good of you. Prices are going up, so it's way better than staring at a plan with unit prices from years ago. With me so far?

The dangerous half has two parts.

The first is using 7% as "the rate for every year from now on." The October domestic corporate goods price index the Bank of Japan put out on November 12, 2026 was up 7.1% from a year earlier. That's a snapshot of how much prices rose over the past year. It's not a forecast. If you go back through the tables in the same release, a year earlier, in October 2025, it was 2.8%, and in February 2026 it was 2.2%, and then it jumped to 5.5% in April and 7.7% in July. A rate that more than tripled in under half a year, and you set it as the same for 10 years ahead? That's a stretch, right? Let's try multiplying work you've scheduled for 10 years from now by 7% every year. 1.07 to the 10th power is about 1.97 times, almost double today's quote. Do the same calculation with the 2.8% from a year earlier and it's about 1.32 times. Just which month you made the plan in changes the estimate this much. Stretch one year of growth over 10 years, and the snapshot turns into a forecast. Get it?

No, it's right, putting the rise into the estimate is right, but the problem is how you put it in.

The second one matters more. If you multiplied your expenses by 7%, what percentage are you multiplying your income by? Even if repair costs go up, rent doesn't go up automatically. Rent is decided by what tenants can pay and by the rent of similar units nearby. Looking at the Ministry of Internal Affairs and Communications' consumer price index, rent for privately owned housing in September 2026 was up 0.8% from the same month a year earlier. Compared with the 7.1% for corporate goods prices, that's much slower. Sometimes it's right to inflate only the expenses with prices and leave income at current rent. But then the estimate of your cash left over goes down. Looking at that lower number and deciding whether you'll still keep holding the property is the real work. Did you notice?

Well, then again, if you've added the same 7% to rent too and made it "break even," that's the more dangerous one. The 0.8% is a national average, and how rent rises is totally different depending on a property's location and age.

"Didn't you just say multiplying by a rate is dangerous?" I didn't say don't multiply. I'm saying if you multiply, put a rate with a basis on each of expenses and income.

So there's one thing to check. In the table where you fixed the repair cost estimate, what rate did you put on the rent estimate? Can you write the basis for that rate in one line? If you can't, that's the biggest hole. Well?

Honestly, price figures are like the heat under a hot pot. If you only look at the high heat right now and write the recipe assuming high heat until the end, it'll burn, or you'll run short of ingredients. A winter hot pot is something you taste along the way and add to.

Sources (in Japanese)

(Updated 2026.11.13)
Jamie GooInvestor in training

Hey, it's Jamie! When I hear "repair cost estimate," I remember the error beep of a water heater. Beep-beep, beep-beep. That sound on a winter morning!

At a used condominium unit I own, I got a message from the tenant: "There's no hot water." The building is a little over 20 years old. The water heater there is an electric water heater, it had been replaced once under the previous owner, and the quote from that time was among the documents I took over. I looked at it, thought "if I replace it, it'll be this price," and copied it straight into the repairs column of my notebook. I didn't look at the date. I was completely convinced that as long as I had the amount written down, I was perfectly prepared!

But the quote from the contractor who came out was about 30% higher than that old quote. Without thinking, I showed them the old one and said, "Last time it was this price." The contractor pointed at the date and asked, "How many years ago is this from?" The date on the quote was long before I bought the unit. Both the price of the equipment and the cost of the labor had gone up in the meantime.

On top of that, when a water heater breaks, it can't wait. In a unit with no hot water in winter, you can't tell the tenant, "Please wait 1 week so I can get competing quotes." I asked for the work that same day. The moment something breaks, the time to compare whether it's expensive or cheap disappears.

Later I read the Bank of Japan's corporate goods price release. In October 2026, domestic corporate goods prices were up 7.1% from a year earlier. So what about my electric water heater? I looked, and "electric water heaters and water heating appliances" fall under a group called electrical machinery and equipment, which was up 6.7% from a year earlier. Great, this solves the mystery of the 30%! I thought, but it doesn't. That's one year's rise, and it's only about equipment shipment prices. My old quote was from years ago, and the bill also included the labor for installation and disposal of the old unit. No matter how long you stare at one year's rate, it won't check the answer on a quote that sat around for years!

There are three things I'd like to tell myself back then.

  • With a quote you took over, look at the date before the amount
  • For equipment like water heaters that can't wait once they break, get a quote at today's price once before they break
  • "Last time it was this price" isn't a phrase that lowers the price. It's a phrase that confesses your preparation was out of date

By the way, since that winter, in the repairs column of my notebook I write "as of when" along with the amount. Thanks to that, my notebook is starting to look like a timeline. Maybe the one who knows the history of prices best is my notebook!

Sources (in Japanese)

(Updated 2026.11.13)